A knockdown rebuild is the demolition of your existing home and the construction of a new home on the same property. This type of building gives you the ability to keep your location, your street and your neighbours, while getting a home that more closely meets your requirements. According to the Australian Bureau of Statistics (ABS), 19.2% of residential dwellings approved in Australia between July 2019 and June 2025 were associated with knock-down rebuild projects. This highlights the significant role of knock-down rebuilds in Australia’s housing market.

The process looks long on paper, but it comes down to five stages. Demolition sits in the middle and everything after it waits on it, so it pays to understand that part early. What follows is the whole job in order, from where we stand on site.

Stage 1: Planning and pricing

The NSW Government’s myHome Planner guide for knockdown rebuilds starts with the unglamorous stuff: finances, site inspections, and choosing your builder or demolition contractor. Notice the “or”. On plenty of projects the demolition contractor is chosen separately from the builder.

Get the demolition priced early. A site inspection tells us about access, what the house is made of, how much old slab and foundation is in the ground, and whether asbestos is likely. All of that moves the budget, and none of it shows up on a floor plan. We give one fixed price after the inspection, so you know the demolition number before you commit to the rest of the project.

Stage 2: Approvals

Demolition and construction need separate applications. Demolition goes through either a development application (DA) or a complying development certificate (CDC), and the new house has its own approval path. Some projects fold demolition into the application for the new home, so ask your builder or designer before you pay for two. We’ve covered the difference in our guide to demolition approvals in Sydney.

If the house is older, add the asbestos question to this stage too. Testing before you quote or apply saves surprises later.

Stage 3: Demolition

Once the approval is issued, your neighbours have to be told in writing before work starts. That’s the owner’s job, and the notice period is at least seven days in metropolitan areas.

Then the site gets ready. Power, water, gas and telecommunications are disconnected, safety fencing goes up, and any council conditions are met. We handle that as part of pre-demolition setup. If there’s asbestos, it comes out first.

After that the structure comes down. Most of our jobs use excavators with demolition attachments, sized to the block, because a lot of Sydney sites have tight access or shared driveways. Where a machine can’t reach, we fall back to partial hand demolition for those sections. Timber, brick, concrete, metal and roofing are sorted on site and sent for recycling wherever possible. When it’s done the block is clear and level.

A straightforward residential demolition can take several days. Larger or more complicated sites take longer. You can read more about how we run house demolition jobs on its own page.

Stage 4: Clearing and preparing the block

The NSW guide describes this stage as the site being cleared for construction, with the construction certificate, a principal certifier and lender approval to sort out before the build begins.

Our side of it is the ground. If your builder wants the block dug, levelled and graded ready for footings, that’s site excavation, including removing old foundations, slabs and underground services where needed. It’s worth settling in writing who does that before demolition starts, because it’s the grey area between where demolition ends and the build begins.

An empty block still needs looking after. Fencing and signage have to stay up to keep people away from hazards like open pits and uneven ground, and it also helps stop illegal dumping.

Stage 5: The build and handover

The builder takes over from here. The last steps in the NSW guide are a pre-handover inspection and applying for an occupation certificate. It’s not our part of the job, but the block we hand over is the block your builder starts on. That’s why we schedule demolition against the builder’s construction start date rather than treating it as a standalone job.

Who arranges the demolition?

It depends on your contract. Many builders expect the owner to organise it, and others work with a demolition contractor they already know. We work with both homeowners and builders.

Whoever ends up organising it, agree the scope in writing. That means what’s coming out (the house, garage, sheds, carports and any in-ground pool), whether slabs and footings are included, what happens with trees, and who levels the block at the end.

Where the time and money go

Two houses on the same street can need very different demolitions, which is why published price ranges are so wide and why we price after an inspection. The things that move the number most are:

  • Access to the block, including narrow frontage and shared driveways
  • What the house is made of, whether that’s weatherboard, brick veneer, double brick or fibro
  • Asbestos, and how much of it there is
  • Old slabs, footings, pools and underground services
  • Trees and any council conditions

Delays typically occur with regards to approvals, asbestos, neighbour notices, and builder start dates. With regards to the start of construction, most of these can be managed if you work backwards from the date you want construction to begin.

Is a knockdown rebuild the right call?

In our experience the houses that end up as knockdown rebuilds are the ones with expensive problems, such as asbestos throughout, structural trouble or a layout that can’t be changed, on a block that’s worth keeping. If a renovation can fix what bothers you, you probably don’t need to demolish anything. Either way, an inspection and a fixed demolition price gives you a real number to compare.

FAQs

Does the demolition contractor leave the block ready for the builder? 

The block is left clear and level. Digging, grading and removing old foundations for new footings is a separate step, which we can do as part of site excavation.

Can I get a demolition quote before I’ve chosen a builder? 

Yes. We inspect the property and give you a fixed price, and you don’t need a builder lined up first. It’s a useful number to have when you’re comparing builders.

Are demolition and construction approved together? 

Usually they’re separate applications, though some projects bundle them. Ask your builder or designer. There’s more in our FAQs.

Planning a knockdown rebuild?

Send us the address and we’ll book a site visit, usually within a few days. You can see how the whole job runs in our process, or browse our services. 