In NSW, knocking down a house counts as development, so you need approval before anyone starts work. The part that catches people out is which approval. There are two main routes: a development application (DA) through your council, or a complying development certificate (CDC) from a certifier. Your property decides which one is open to you.

Below is how the two routes differ, what paperwork gets asked for, and the bits people tend to forget until the excavator is already booked.

DA or CDC: what’s the difference?

A DA goes to your local council. They assess it and they decide, so the timing sits on their side of the table.

A CDC skips the council assessment. If the demolition meets the rules in the NSW Exempt and Complying Development Codes, your council or an accredited private certifier can issue the certificate once they’ve checked the paperwork. A properly lodged CDC doesn’t get advertised for comment, which is a big part of why it’s quicker.

The catch is that not every block qualifies. Your section 10.7 planning certificate lists the planning controls on your land, and it’s the first document to get. You can order one online through the NSW Planning Portal. Your council or certifier reads it to work out which route is open.

There’s a third category, exempt development, where no approval is needed at all. It’s narrow. It covers things like a small shed that was itself built as exempt development. A house doesn’t qualify.

When you’re probably looking at a DA

Heritage is the big one in Sydney. If your house is a heritage item, or it sits in a heritage conservation area, a CDC is generally off the table, and councils commonly ask for a statement of heritage impact with the application. Plenty of Sydney suburbs have conservation areas that cover whole streets, so check your address before you assume anything.

The Codes also rule out some other types of land, such as certain foreshore, environmentally sensitive and protected areas. Your 10.7 certificate will flag these.

One more thing to ask about. Sometimes the demolition is folded into the DA for the new house. If your builder or designer is lodging a DA for the rebuild, find out whether demolition is already in it before you pay for a second application.

What you’ll be asked for

Whichever route you take, expect to hand over a few things:

  • Your section 10.7 planning certificate
  • A site and survey plan showing what’s on the block now
  • A waste management plan, which covers what leaves the site and where it ends up (our recycling page explains how we sort it)
  • The demolition contractor’s licence and insurance details, if the building is over 6 metres high

Your council can also ask for a security deposit, held against damage to council property like footpaths and kerbs.

What the approval doesn’t cover

An approval gives you the right to demolish. A handful of other jobs still need sorting separately.

Trees. Ring your council before you remove or prune anything on the block, because trees can need their own approval.

Services. Power, gas, water, sewer and telecommunications all have to be disconnected by licensed people before demolition starts. Gas and internet are a call to your supplier. Water and sewer usually go through your demolition contractor. It’s also worth lodging a free enquiry with Before You Dig Australia so you know what’s buried on the block. We cover disconnections, fencing and council conditions in our pre-demolition setup.

Neighbours. Once the approval is issued, you have to notify neighbours within 20 metres of your boundary, in writing. In metropolitan areas that means at least seven days before work starts. This one is the owner’s job, which surprises a lot of people. Get the letters out as soon as the approval lands, because a missed notice period pushes your start date.

Fencing and the street. Temporary fencing with signage has to go up around the site. Hoarding or scaffolding on a footpath or road needs its own approval from the council or Transport for NSW.

Asbestos can change your timeline

Council guidance treats 1987 as the line: if the house was built before that, assume there could be asbestos. We’d stretch that to the early 1990s in practice, because fibro sheeting, eaves, vinyl flooring and roofing from those years often contain it.

If there’s more than 10 square metres of non-friable asbestos, a licensed asbestos removalist has to do the job and SafeWork NSW needs to be told. After removal, an independent assessor issues a clearance certificate before general demolition can carry on.

Finding asbestos halfway through a job costs more, in both time and money, than finding it at the start. That’s why we check at the site inspection and arrange testing or licensed asbestos removal before the machines turn up.

How long does it take?

It depends on the route. A CDC can often come through within a few weeks once the certifier has everything. A DA takes longer, and the council sets the pace. Add the neighbour notice, plus any asbestos work that has to finish first.

Once all that’s done, the demolition itself is the short part. A straightforward house can be down in several days, though access, construction type and site conditions change that.

If a builder is waiting on your block, work backwards from their start date and get the approval moving early. On knock down rebuilds we schedule demolition against the builder’s construction start, and that’s much easier when we hear about the job early. You can see how a project runs from site visit to handover.

Who actually lodges the application?

Usually the demolition contractor or a certifier, not you. NSW’s own planning guidance says the contractor typically submits the demolition application. At Next Home Demo we check which pathway applies to your property during the site visit, then coordinate the approvals and the pre-demolition requirements so you’re not chasing it yourself. Our house demolition service covers the work from there, and if the block needs digging out afterwards, that’s site excavation.

FAQs

Can I start before the approval comes through? 

No. Unless the work is exempt, the DA or CDC has to be in place first. Starting early puts you on the wrong side of the planning rules, and the job can be stopped.

What if my house is heritage listed? 

You’ll be going down the DA route, and councils take heritage seriously, so approval for a full demolition isn’t guaranteed. Speak to your council before you spend money on anything else.

Does a demolition quote include the approvals? 

Not always. Some quotes cover the machine work only, some leave out asbestos, and some leave out the paperwork. Ask what’s in and what isn’t, and get it in writing. Ours is one fixed price after we’ve inspected the property, covering demolition, disposal and site clean-up. There’s more in our FAQs.

Not sure which route your block needs?

Send us the address and we’ll take a look. Call 1300 220 032 or use the contact page to book a free quote. You can also see the full list of our services.

Leave a Reply

Your email address will not be published. Required fields are marked *